Review Agenda Item
Meeting Date: 8/22/2023 - 6:30 PM
Category: Finance - Board Liaison, Darren Mariano
Type: Action
Subject: 7.5 Change Order: High School Stadium-Track
:
Enclosure
File Attachment:
CVHS Stadium Renovations Track Binder and Base Repairs.pdf
Summary: Motion to approve the change order for the High School Track in the amount of $158,500.00. For the High School Exterior Athletics, a remaining hard cost contingency of $177,074.16 and a contingency balance of $18,574.16 remains. Approximately 7.2% of the hard cost contingency remains.
Funding: Bond Fund 2021
Recommendation for the Board Action: For Board approval.