4.4 Approve Change Order PS HVAC-Lugaila Mechanical, Inc. #3
|
:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
Motion to approve Lugaila Mechanical, Inc. change order #3 for an addition of $9,661.60. There is currently a remaining hard cost contingency of $218,755.00 for the PS HVAC project. Following the approval of proposed change orders a contingency balance of $174,607.30 remains for this project. Approximately 76.5% of the original hard cost contingency will remain following approval.
|
Funding:
|
Bond Fund 2021
|
Recommendation for the Board Action:
|
For Board approval.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Patricia Connolly - Director of Finance & Operations
|
|
Signed By:
|
|
Johannah Vanatta - Superintendent
|
|
|
|
|
|
|
|