4.5 Change Orders - High School Exterior Athletics and PS HVAC
|
:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
Motion to approve the change orders for High School Exterior Athletics and Primary School HVAC. For High School Exterior Athletics, a remaining hard cost contingency of $258,806.16 and a contingency balance of $177,074.16 remains. Approximately 68% of the hard cost contingency remains.
For the PS HVAC, a remaining hard cost contingency of $228,285.00 and a contingency balance of $218,755.00 remains for this project. Approximately 95% of the hard cost contingency will remain.
|
Funding:
|
Bond Fund 2021
|
Recommendation for the Board Action:
|
For Board approval.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Patricia Connolly - Director of Finance & Operations
|
|
Signed By:
|
|
Johannah Vanatta - Superintendent
|
|
|
|
|
|
|
|