Agenda Item
Meeting Date:
9/12/2023 - 6:30 PM  
Category:
Budget & Finance  
Type:
Action  
Subject:
4.6 Change Order - High School Exterior Athletics GC-005  
:
 
Enclosure:
 
File Attachment:
Change Order Ratify Report GC-005.pdf
 
Summary:
Motion to approve Change Order GC-005 for cost associated with upgrades to the exterior finishes of the existing electrical room which will remain. The total cost of the upgrade to the existing electrical room exterior is $70,788.00. The original hard cost budget contingency for this project was $258,283.70. Prior to the approval of this change order, the remaining hard cost contingency was $39,169.70. Following the approval of this change order, the remaining hard cost contingency will be (-$31,618.30). At this time, the remaining soft cost contingency of $38,389.36 will be used to re-balance out the budget.  
Funding:
Bond Fund 2021  
Recommendation for the Board Action
For Board approval.  
Approvals:
Recommended By:
Signed By:
Courtney Saxon - Board Secretary
Signed By:  
Johannah Vanatta - Superintendent